Brictec KTB Fired Brick Production Line Project - July Site Construction Progress Report

2026-07-24
Latest company news about Brictec KTB Fired Brick Production Line Project - July Site Construction Progress Report
I. Project Introduction

Brictec KTB fired brick production line project. This project plans to construct three modern tunnel kiln fired brick production lines, to be carried out in three phases. After Phase I and Phase II are put into operation, the expected total daily output will reach 900 tons, mainly producing clay fired bricks with dimensions of 240*115*75 mm.

II. Current Progress

The KTB project is currently in the construction stage of the tunnel kiln roof and the drying chamber, as shown in the figures below.

ข่าว บริษัท ล่าสุดเกี่ยวกับ Brictec KTB Fired Brick Production Line Project - July Site Construction Progress Report  0

ข่าว บริษัท ล่าสุดเกี่ยวกับ Brictec KTB Fired Brick Production Line Project - July Site Construction Progress Report  1

ข่าว บริษัท ล่าสุดเกี่ยวกับ Brictec KTB Fired Brick Production Line Project - July Site Construction Progress Report  2

ข่าว บริษัท ล่าสุดเกี่ยวกับ Brictec KTB Fired Brick Production Line Project - July Site Construction Progress Report  3